Market: Pharmaceutical
Location: Ann Arbor, Michigan
Customer: Pfizer
Project: Building 25 AHU Modifications
Completion: Winter 2003

The pharmaceutical industry has stringent quality standards and operating guidelines for HVAC equipment. Pfizer, a household name in Pharmaceuticals, was experiencing severe stratification problems in 6 of their existing Air Handling Units. Stratification is caused by improper air distribution and results in inadequate heating and cooling.

Pfizer hired TMI to survey and present solutions that would solve the problem after the original air handler manufacturer left the project. TMI’s on site service technicians and engineering staff were able to solve the problem by designing and fabricating a custom air distribution wall that eliminated the stratification problems they were experiencing.

Finding the solution to the problem was only part of the challenge. Executing the project without interrupting Pfizer’s day-to-day operation was critical to making this project a success. All of the work was performed after hours and on weekends to provide “Total Customer Satisfaction”.

TMI is unsurpassed in evaluating the situation, designing a solution and completing the project on time.